Town of Cohasset DPW Water Main Replacement Notice

Elm Detour

The Town of Cohasset wishes to take this opportunity to notify you that we are approaching the anticipated start of a water main replacement project in your neighborhood as a reminder of the scope of work proposed and what can be expected during the course of construction.

Where: The Town of Cohasset contractor will begin installation of a new 8" ductile iron water main to replace the existing water main.

Who: The Town of Cohasset Department of Water Department has contracted the construction work to Gravity Construction. An inspector for the Town will regularly be on-site overseeing and inspecting the construction.

When: The anticipated start for the project is week of October 11, 2021 with a projected duration of 7 weeks. Weather and/or construction delays may impact this schedule.

How: In general, work will consist of the following:

  • Grind the limits of the proposed trench (when applicable) where the new water main will be installed;
  •  Excavate to install the new water main;
  •  Backfill the excavations & install temporary pavement;
  •  Pressure test and chlorinate the main line pipe.
  •  Tie in all streets and service line to new main.
  •  Final paving is scheduled to be done next year to allow for any trench settlement.

What: In general, the following can be expected during construction:

  •  There will be a heavy presence of construction noise, vehicles, equipment, & materials during construction hours;
  •  Normal working hours will be from 7AM to 4PM. There will be detours in place to provide a safer construction zone. Elm Street Detour Map