Capital Project
Little Harbor, Atlantic Avenue, Deep Run & Rust Way Sewer Expansion
The remaining balance of the $15,200,000 borrowing capacity previously approved by Town Meeting is $46,754. The Town Manager commissioned an independent firm to complete a full audit of the appropriation. A report dated October 22, 2012 confirms all expenditures for the Little Harbor Water and Sewer Project, and final close-out construction contracts in progress.