August 18, 2017-Bound Brook Update- Paving will be completed today. Concrete sidewalk and fencing will continue into next week, as well as other items for completion.

August 17, 2017 - Bound Brook Update - TRAFFIC ALERT Paving is scheduled to occur Friday, August 18th from 7AM to 7PM.  Paving is scheduled to occur Friday, August 18th from 7AM to 7PM.  Work will include fine grading of the gravel subgrade, installation of asphalt base course, followed by installation of the top asphalt course.  One lane will be open to traffic, but you should expect delays.

August 15, 2017 -Bound Brook Update - Guardrail installation work on Beechwood Street at Bound Brook Dam will occur overnight tonight Tuesday, August 15th and Wednesday night, August 16th.

Curb installation will occur on both Wednesday and Thursday as well. This will be followed by road paving scheduled for Friday August 18th. Traffic will be impacted in the area, so please plan accordingly.

More detailed traffic impact information will be posted again on Thursday.  We apologize for any disruption as the final stages of this project are completed.  